Unsolved

This post is more than 5 years old

1841

August 11th, 2017 08:00

Failover / Failback Control Station in VNX5300

I have a problem with the import connection between Unity and VNX.

I found an article to solve my problem: KB 000489181

https://emcservice.force.com/CustomersPartners/KB_BreakFix_clone?id=kA2j00000004Gy7

I need to perform a failover on a VNX5300 Unified,

I need to know if this causes any loss of connection with the clients of the CIFS servers.

Performing a failover generates some unavailability of data from CIFS servers?

I will be grateful for your answers.

Regards

169 Posts

August 14th, 2017 16:00

No, failover on VNX is fine. Ofcourse for the duration of failover (and cifs server becoming active on standby), there may be an impact.

If this is in Initialization, VNX CIFS Server is still in production. If this is during Incremental copy, there will be an impact with writes/some reads.

No Events found!

Top