ECC 5.2 to SP5 Upgrade - Clariion Cx3-80 Discovery
I am going to start upgrading the control center to version 5.2 SP5 from its current version SP3. I currently have two new Clariions to manage and they are not supported in SP3. When I install SP5 do I need to add an additional Clariion Agent for the Cx3-80's or just install the latest NAVI-CLI on the existing hosts and then upgrade the agent on those?
No Events found!
bodnarg
2 Intern
•
385 Posts
0
October 25th, 2007 05:00
Depending on the size/number of Clariions you may need to deploy another Clariion agent to handle the chatter (especially if you have WLA and a lot of alerts) but my guess is unless you have a lot of older Clariions you should be fine.
With the CX3 you should actually be able to do more management with the Clariion agent - we have CX500s in our environment and the Clariion agent really just lets us do some very basic control and reporting only.
bodnarg
2 Intern
•
385 Posts
1
October 25th, 2007 05:00
As long as the NAVI-CLI version is compatible you should be able to leverage the single Clariion agent to manage both the old and new units.