Hi. I am implementing Policy Manager for my existing ESRS environment and would like to do some testing and configuration before I 'go live' with the policies. I have ESRS VE v3 gateways and see where to enable the use of PM, but was wondering if it would cause issues if I enabled PM in order to populate the assets, set up the groups and policies, but then un-check it at the gateway while I work with it and until I'm ready to go into production. I want to ensure that this activity will not disrupt ESRS call home functionality through the gateways, which is currently working well. As a side question, if PM does not work as expected, can it be disabled in the same manner until fixed? Has anyone tried this? Thanks for the help. DB



RPE
33 Posts
0
February 13th, 2017 06:00
You can enable the PM in the ESRS-VE GUI, and the PM will be populated with all assets.
If you then uncheck the PM in the ESRS-VE GUI, the default application behavior is to go "always allow".
Same can be done if the PM does not work as expected, does not function at all or is unreachable from the ESRS-VE .