Computer room relocation

We have two sites, Site A and Site C, Site A and Site C. The CG is done by RPA. We want to relocate the storage devices at Site C. What preparations should we make?

13 Posts

October 12th, 2019 23:00

It's similar to a power shutdown activity. Since you have 4 copies technically of your CGs, not much of a worry.

Just ensure to pause/disable the CGs prior to powering off.