Setting Retention date post upload

Hello Experts,

I need to know can we set retention date for data which is already in centera.

Can this be done programatically or thru any scripting if its possible

Thanks in advance.

Prashant

337 Posts

July 15th, 2011 00:00

Hi,

Setting retention for data which is already stored in centera is not possible; it can be set only with the new data to be written into it.

If setting the retention is a priority, than the data can we re-written to a new profile with the custom retention.