This post is more than 5 years old
6 Posts
0
1329
December 10th, 2014 01:00
checkpoints celerra pause
Hi,
I have a problem, have ckpt :
nas_ckpt_schedule -list
Id Name State Next Run Description
2 sched_CajonDesastre Active Wed Dec 10 17:35:00 CET 2014
3 sched_CajonDesastre2 Paused Wed Dec 10 17:35:00 CET 2014
4 sched_CajonDesastre3 Paused Wed Dec 10 17:20:00 CET 2014
5 sched_CajonDesastre4 Paused Wed Dec 10 17:50:00 CET 2014
14 sched_CajonDesastre5 Paused Fri Dec 12 18:15:00 CET 2014
6 sched_COMUNICACIONES Paused Wed Dec 10 17:30:00 CET 2014
11 sched_FS_UNIDADES1 Active Wed Dec 10 17:50:00 CET 2014
7 sched_HOME Paused Wed Dec 10 17:30:00 CET 2014
13 sched_nasproyectos Active Mon Dec 15 18:30:00 CET 2014
9 sched_SGDT_CAMINOS Paused Wed Dec 10 17:45:00 CET 2014
10 sched_SISTEMAS Paused Wed Dec 10 17:40:00 CET 2014
as I can re-activate?
I activated the filesystem deduplication
and I get errors espacion of SavVol
any suggestions?
Thanks!